With the insulating render, how long should I leave before apply the fine render top coat or can I apply the top coat the following days? Also how long after top coat can I apply mineral paint?
Cornish Lime Changed status to publish July 20, 2022
Thanks for getting in touch. Ideally you would apply the topcoat the following day. If this isn’t achievable then allow 7 days between coats.
You will need to allow a minimum of 4 to 6 weeks before painting.